[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-857964":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},857964,535,1,"单选题","初步设计阶段BIM应用不包括()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程算量",false,{"key":16,"text":17,"correct":14},"B","结构分析",{"key":19,"text":20,"correct":14},"C","性能分析",{"key":22,"text":23,"correct":24},"D","结构优化",true,"初步设计阶段BIM应用主要包括结构分析、性能分析和工程算量。",{"id":6,"name":27,"category":28,"favorite":29},"BIM工程师","建筑工程",0]