[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-857956":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},857956,535,1,"单选题","下列关BIM在钢结构深化设计中的应用说法错误的是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","钢结构BIM三维实体建模出图进行深化设计的过程，其本质就是进行电脑预拼装，实现“所见即所得”的过程",false,{"key":16,"text":17,"correct":14},"B","所有加工详图(包括布置图、构件图、零件图等)均是利用三视图原理投影剖面生成的深化图纸",{"key":19,"text":20,"correct":14},"C","采用BIM技术对钢网架复杂节点进行深化设计，提前对重要部位的安装进行动态展示、施工方案预演和比选，可以更加直观化的传递施工",{"key":22,"text":23,"correct":24},"D","意图，避免二次返工",true,"钢结构三维实体建模出图进行深化设计的过程，基本可分为四个阶段：搭建BIM三维模型，基于模型对结构节点进行补充和安装，碰撞校核，基于BIM模型出图。",{"id":6,"name":27,"category":28,"favorite":29},"BIM工程师","建筑工程",0]