[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-857925":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},857925,535,1,"单选题","项目后评价的步骤为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","提出问题→筹划准备→深入调查，搜集资料→分析研究→编制项目后评价报告",true,{"key":16,"text":17,"correct":18},"B","提出问题→深入调查，搜集资料→筹划准备→分析研究→编制项目后评价报告",false,{"key":20,"text":21,"correct":18},"C","提出问题→筹划准备→分析研究→深入调查，搜集资料→编制项目后评价报告",{"key":23,"text":24,"correct":18},"D","提出问题→深入调查，搜集资料→分析研究→筹划准备→编制项目后评价报告","项目后评价的流程。",{"id":6,"name":27,"category":28,"favorite":29},"BIM工程师","建筑工程",0]