[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-857915":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},857915,535,1,"单选题","工程变更指的是针对哪一类工程进行变更()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","还未进行方案设计的工程",false,{"key":16,"text":17,"correct":14},"B","处于方案前期设计阶段的工程",{"key":19,"text":20,"correct":14},"C","设计方案已确定但还未投入施工的工程",{"key":22,"text":23,"correct":24},"D","已经正式投入施工的工程",true,"工程变更的定义。",{"id":6,"name":27,"category":28,"favorite":29},"BIM工程师","建筑工程",0]