[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-857905":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},857905,535,1,"单选题","下列选项不属于设计阶段的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","方案设计阶段",false,{"key":16,"text":17,"correct":14},"B","初步设计阶段",{"key":19,"text":20,"correct":14},"C","施工图设计阶段",{"key":22,"text":23,"correct":24},"D","深化设计阶段",true,"BIM在设计管理中的任务和应用清单中可以知道设计阶段分为方案设计阶段、初步设计阶段和施工图设计阶段。",{"id":6,"name":27,"category":28,"favorite":29},"BIM工程师","建筑工程",0]