[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-857901":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},857901,535,1,"单选题","供货单位的项目管理的目标不包括()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","供货单位的成本目标",false,{"key":16,"text":17,"correct":18},"B","供货单位的利润目标",true,{"key":20,"text":21,"correct":14},"C","供货的进度目标",{"key":23,"text":24,"correct":14},"D","供货的质量目标","供货单位作为项目建设的一个参与方，其项目管理主要服务于项目的整体利益和供货单位本身的利益。其项目管理的目标包括供货单位的成本目标、供货的进度目标和供货的质量目标。",{"id":6,"name":27,"category":28,"favorite":29},"BIM工程师","建筑工程",0]