[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-857886":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},857886,535,1,"单选题","下列选项中不属于基于BIM的土建结构深化设计内容的是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","门窗等构件施工图深化",false,{"key":16,"text":17,"correct":14},"B","预留洞口及预埋件位置深化",{"key":19,"text":20,"correct":21},"C","管线支吊架深化",true,{"key":23,"text":24,"correct":14},"D","解决关键复杂墙板的钢筋绑扎顺序及绑扎位置等问题","基于BIM模型对土建结构部分，包括土建结构与门窗等构件、预留洞口、预埋件位置及各复杂部位等施工图纸进行深化，对关键复杂的墙板进行拆分，解决钢筋绑扎、顺序问题，能够指导现场钢筋绑扎施工，减少在工程施工阶段可能存在的错误损失和返工的可能性。",{"id":6,"name":27,"category":28,"favorite":29},"BIM工程师","建筑工程",0]