[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-857874":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},857874,535,1,"单选题","在BIM三维模型信息的基础上，增加一维进度信息，这种基于BIM的管理方式称为()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","可视化管理",false,{"key":16,"text":17,"correct":14},"B","多维管理",{"key":19,"text":20,"correct":21},"C","4D管理",true,{"key":23,"text":24,"correct":14},"D","信息化管理","在BIM三维模型信息的基础上，增加一维进度信息，我们将这种基于BIM的管理称为4D管理。",{"id":6,"name":27,"category":28,"favorite":29},"BIM工程师","建筑工程",0]