[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-857856":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},857856,535,1,"单选题","( )是为了保证完成项目的实际成本、费用不超过预算成本、费用的管理过程。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目质量控制",false,{"key":16,"text":17,"correct":18},"B","项目成本管理",true,{"key":20,"text":21,"correct":14},"C","项目范围管理",{"key":23,"text":24,"correct":14},"D","项目时间管理","项目管理内容中对项目成本的解释。",{"id":6,"name":27,"category":28,"favorite":29},"BIM工程师","建筑工程",0]