[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-857847":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},857847,535,1,"单选题","下列选项关于碰撞检查的顺序说法正确的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","首先进行设备内部各专业碰撞检测，然后进行土建碰撞检测，之后进行结构与给排水、暖、电专业碰撞检测等，最后解决各管线之间交叉问题",false,{"key":16,"text":17,"correct":18},"B","首先进行土建碰撞检测，然后进行设备内部各专业碰撞检测，之后进行结构与给排水、暖、电专业碰撞检测等，最后解决各管线之间交叉问题",true,{"key":20,"text":21,"correct":14},"C","首先进行土建碰撞检测，然后进行结构与给排水、暖、电专业碰撞检测等，之后进行设备内部各专业碰撞检测，最后解决各管线之间交叉问题",{"key":23,"text":24,"correct":14},"D","首先进行结构与给排水、暖、电专业碰撞检测等，然后进行设备内部各专业碰撞检测，之后进行土建碰撞检测，最后解决各管线之间交叉问题","在对项目进行碰撞检测时，要遵循如下检测优先级顺序：首先，进行土建碰撞检测；然后，进行设备内部各专业碰撞检测；之后，进行结构与给排水、暖、电专业碰撞检测等；最后，解决各管线之间交叉问题。",{"id":6,"name":27,"category":28,"favorite":29},"BIM工程师","建筑工程",0]