[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-857828":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},857828,535,1,"单选题","BIM在工程项目进度管理中的应用体现在项目进行过程中的方方面面，下面不是其关键应用点的是？()",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工进度计划编制",false,{"key":16,"text":17,"correct":14},"B","BIM施工进度4D模拟",{"key":19,"text":20,"correct":14},"C","BIM施工安全与冲突分析系统",{"key":22,"text":23,"correct":24},"D","BIM施工成本控制",true,"进度管理。",{"id":6,"name":27,"category":28,"favorite":29},"BIM工程师","建筑工程",0]