[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-857822":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},857822,535,1,"单选题","设计阶段BIM管理者通过()对项目进度实施有效的动态管理。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","网络协同工作方式",true,{"key":16,"text":17,"correct":18},"B","链接的方式",false,{"key":20,"text":21,"correct":18},"C","参照的方式",{"key":23,"text":24,"correct":18},"D","二维协同方式","管理者通过网络协同工作方式对项目进度实施有效的动态管理。",{"id":6,"name":27,"category":28,"favorite":29},"BIM工程师","建筑工程",0]