[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-857806":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},857806,535,1,"单选题","基于BIM的深化设计通过各专业工程师与设计公司的分工合作优化能够针对设计存在问题，迅速对接、核对、相互补位、提醒、反馈信息和整合到位，其深化设计流程为()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","制作专业精准模型→综合链接模型→数据集成→碰撞检测→分析和修改碰撞点→最终完成内装的BIM模型",false,{"key":16,"text":17,"correct":14},"B","制作专业精准模型→碰撞检测→分析和修改碰撞点→综合链接模型→数据集成→最终完成内装的BIM模型",{"key":19,"text":20,"correct":21},"C","制作专业精准模型→综合链接模型→碰撞检测→分析和修改碰撞点→数据集成→最终完成内装的BIM模型",true,{"key":23,"text":24,"correct":14},"D","制作专业精准模型→碰撞检测→分析和修改碰撞点→数据集成→综合链接模型→最终完成内装的BIM模型","综合管线深化设计流程示意图。",{"id":6,"name":27,"category":28,"favorite":29},"BIM工程师","建筑工程",0]