[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-857786":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},857786,535,1,"单选题","设计方的项目管理工作主要在哪个阶段进行？()",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工阶段",false,{"key":16,"text":17,"correct":14},"B","动用前准备阶段",{"key":19,"text":20,"correct":21},"C","设计阶段",true,{"key":23,"text":24,"correct":14},"D","设计前的准备阶段","设计方的项目管理工作主要在设计阶段进行，但它也会向前延伸到设计前的准备阶段，向后延伸至设计后的施工阶段、动用前准备阶段和保修期等。",{"id":6,"name":27,"category":28,"favorite":29},"BIM工程师","建筑工程",0]