[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-857777":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},857777,535,1,"单选题","项目管理的内容不包括()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目范围管理",false,{"key":16,"text":17,"correct":14},"B","项目时间管理",{"key":19,"text":20,"correct":14},"C","项目成本管理",{"key":22,"text":23,"correct":24},"D","项目规模管理",true,"项目管理的内容不包括项目规模管理。",{"id":6,"name":27,"category":28,"favorite":29},"BIM工程师","建筑工程",0]