[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-857769":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},857769,535,1,"单选题","下列选项关于深化设计说法不正确的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","深化设计是指在业主或设计顾问提供的条件图或原理图的基础上，结合施工现场实际情况，对图纸进行细化补充和完善",false,{"key":16,"text":17,"correct":18},"B","专业性深化设计应该在建设单位提供的综合性BIM模型上进行",true,{"key":20,"text":21,"correct":14},"C","综合性深化设计指的是对各专业深化设计初步成果进行集成、协调、修订与校核，并形成综合平面图、综合管线图",{"key":23,"text":24,"correct":14},"D","管线综合深化设计是指将施工图设计阶段完成的机电管线进一步综合排布，根据管线的不同的性质、不同的功能和不同的施工要求，结合建筑装修的要求，进行统筹的管线位置排布","BIM技术在深化设计阶段的应用。",{"id":6,"name":27,"category":28,"favorite":29},"BIM工程师","建筑工程",0]