[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-857744":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},857744,535,1,"单选题","以下哪一项不属于BIM技术在工程进度管理上的应用？()",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","可视化的工程进度安排",false,{"key":16,"text":17,"correct":14},"B","对工程建设过程的模拟",{"key":19,"text":20,"correct":21},"C","对工程施工进度的调控",true,{"key":23,"text":24,"correct":14},"D","对工程材料和设备供应过程的优化","BIM技术在工程进度管理上的三方面应用。",{"id":6,"name":27,"category":28,"favorite":29},"BIM工程师","建筑工程",0]