[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-857738":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},857738,535,1,"单选题","按照相关管理规定，我国建设项目在设计阶段的造价控制主要是方案设计阶段的设计估算和初步设计阶段的()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","设计预算",false,{"key":16,"text":17,"correct":14},"B","设计初算",{"key":19,"text":20,"correct":14},"C","设计结算",{"key":22,"text":23,"correct":24},"D","设计概算",true,"设计阶段的造价控制主要是方案设计阶段的设计估算和初步设计阶段的设计概算。",{"id":6,"name":27,"category":28,"favorite":29},"BIM工程师","建筑工程",0]