[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-857720":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},857720,535,1,"单选题","一项目漫游动画模型共是800帧，先设置从300帧到600帧导出，根据“帧\u002F秒”为20，这样这段截取的漫游动画总时间为()",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","15秒",true,{"key":16,"text":17,"correct":18},"B","20秒",false,{"key":20,"text":21,"correct":18},"C","30秒",{"key":23,"text":24,"correct":18},"D","40秒","总时间为(600－300)\u002F20=15秒。",{"id":6,"name":27,"category":28,"favorite":29},"BIM工程师","建筑工程",0]