[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-857622":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},857622,535,1,"单选题","在导出漫游动画的“长度\u002F格式”对话框中，输出长度设置范围，起点为150，终点为600，帧\u002F秒为10，则总时间为()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","10秒",false,{"key":16,"text":17,"correct":14},"B","30秒",{"key":19,"text":20,"correct":21},"C","45秒",true,{"key":23,"text":24,"correct":14},"D","60秒","总时间为(600-150)\u002F10=45秒。",{"id":6,"name":27,"category":28,"favorite":29},"BIM工程师","建筑工程",0]