[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-857510":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},857510,535,1,"单选题","一项目漫游动画模型共是500帧，先设置从200帧到500帧导出，根据“帧\u002F秒”为15，这样这段截取的漫游动画总时间为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","13.3秒",false,{"key":16,"text":17,"correct":18},"B","20秒",true,{"key":20,"text":21,"correct":14},"C","33.3秒",{"key":23,"text":24,"correct":14},"D","75秒","总时间为(500-200)\u002F15=20秒。",{"id":6,"name":27,"category":28,"favorite":29},"BIM工程师","建筑工程",0]