[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-857439":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},857439,535,1,"单选题","下列选项中，属于设计院在BIM造价方面责任的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","负责项目投资控制",false,{"key":16,"text":17,"correct":14},"B","负责进度款拨付、结算",{"key":19,"text":20,"correct":14},"C","负责项目及工程造价的编制、审核",{"key":22,"text":23,"correct":24},"D","负责配合设计各阶段计算投资",true,"设计院在BIM造价方面主要负责配合设计各阶段计算投资。",{"id":6,"name":27,"category":28,"favorite":29},"BIM工程师","建筑工程",0]