[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-857433":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},857433,535,1,"单选题","施工进度将空间信息与()整合在一个可数的4D模型中，直观、精确地反映整个施工过程。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","设计信息",false,{"key":16,"text":17,"correct":14},"B","位置信息",{"key":19,"text":20,"correct":14},"C","模型信息",{"key":22,"text":23,"correct":24},"D","时间信息",true,"施工进度模拟把空间信息与时间信息整合在一个可视的4D模型中，直观、精确地反映整个施工过程。",{"id":6,"name":27,"category":28,"favorite":29},"BIM工程师","建筑工程",0]