[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-857414":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},857414,535,1,"单选题","管理层主要设置()，其主要负责将BIM项目经理的项目任务安排落实到BIM操作人员，同时对BIM项目在各阶段实施过程中进行技术指导及监督。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目经理",true,{"key":16,"text":17,"correct":18},"B","技术主管",false,{"key":20,"text":21,"correct":18},"C","建模工程师",{"key":23,"text":24,"correct":18},"D","分析工程师","项目经理属于领导层，建模工程师及分析工程师属于作业层。",{"id":6,"name":27,"category":28,"favorite":29},"BIM工程师","建筑工程",0]