[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-857392":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},857392,535,1,"单选题","为了保证数据传递的通畅性，在项目BIM实施阶段软件资源配置时，应根据甲方具体要求或与项目各参与方进行协同合理选择软件版本，对不符合要求的版本软件()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","必须放弃使用",false,{"key":16,"text":17,"correct":18},"B","可进行相应的升级",true,{"key":20,"text":21,"correct":14},"C","可不做处理继续使用",{"key":23,"text":24,"correct":14},"D","必须对其进行自主研发","可对其进行相应的升级后继续使用。",{"id":6,"name":27,"category":28,"favorite":29},"BIM工程师","建筑工程",0]