[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-857317":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},857317,535,1,"单选题","下列选项中，关于IDM的说法不正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","IDM是对项目全生命周期所需交换的信息的定义",true,{"key":16,"text":17,"correct":18},"B","IDM是对某特定业务流程所需要交换的信息以及由该流程产生的信息的定义",false,{"key":20,"text":21,"correct":18},"C","IDM全称InformationDeliveryManual",{"key":23,"text":24,"correct":18},"D","IDM是对某个指定项目以及项目阶段所需要交换信息的定义","IDM即使InformationDeliveryManual，是对某个指定项目以及项目阶段、某个特定项目成员、某个特定业务流程所需要交换的信息以及由该流程产生的信息的定义。",{"id":6,"name":27,"category":28,"favorite":29},"BIM工程师","建筑工程",0]