[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-857303":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},857303,535,1,"单选题","下列关于建筑工程信息模型的说法不正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建模精细度应满足建筑工程量计算要求",false,{"key":16,"text":17,"correct":18},"B","在满足项目需求的前提下，应采用LOD300的建模精细度",true,{"key":20,"text":21,"correct":14},"C","建模精细度宜符合施工工法和措施，为施工深化预留条件",{"key":23,"text":24,"correct":14},"D","输入的建筑工程信息应满足现行有关工程文件编制深度规定","在满足项目需求的前提下，宜采用较低的建模精细度。",{"id":6,"name":27,"category":28,"favorite":29},"BIM工程师","建筑工程",0]