[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-857288":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},857288,535,1,"单选题","信息的输入者宜对建筑信息模型的文件或者信息条目添加数据状态标识，以表明交付的有效性，其中()表示已被工程参与方整体认可的有效整体交付数据，可作为阶段性有效成果。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工作数据",false,{"key":16,"text":17,"correct":18},"B","共享数据",true,{"key":20,"text":21,"correct":14},"C","出版数据",{"key":23,"text":24,"correct":14},"D","存档数据","工作数据表示正在进行工作的数据，存在变更的可能。此数据可作为参考，不应作为决策依据。出版数据表示已被工程参与方整体认可的有效整体交付数据，可作为阶段性有效成果。存档数据表示数据符合工程实际情况，已被存档。",{"id":6,"name":27,"category":28,"favorite":29},"BIM工程师","建筑工程",0]