[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-857249":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},857249,535,1,"单选题","施工进度模拟即通过将BIM与()相连接，把空间信息与时间信息整合在一个可视的4D模型中，反映整个施工过程。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工图纸",false,{"key":16,"text":17,"correct":14},"B","深化设计",{"key":19,"text":20,"correct":21},"C","施工进度",true,{"key":23,"text":24,"correct":14},"D","位置信息","施工进度模拟即通过将BIM与施工进度计划相连接，把空间信息与实践信息整合在一个可视的4D模型中，直观、精确地反映整个施工过程。",{"id":6,"name":27,"category":28,"favorite":29},"BIM工程师","建筑工程",0]