[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-857223":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},857223,535,1,"单选题","下列关于传统方法和BIM技术在工程项目进度管理的应用的说法中不正确的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","三维模型的可视化有效地解决了施工人员的读图问题，可减少施工成品与设计图纸不符的现象发生",false,{"key":16,"text":17,"correct":14},"B","三维模型的碰撞检查能够有效规避设计成果中的冲突和矛盾，从而缓解二维图纸很难检查错误和矛盾的问题",{"key":19,"text":20,"correct":21},"C","BIM可以解决劳动力不足以及消极怠工问题",true,{"key":23,"text":24,"correct":14},"D","BIM技术的应用可以缓解进度计划编制中存在的问题","劳动力不足以及消极怠工的问题是由于实际条件限制和主观因素造成的，无法通过改进工具和技术得到解决。",{"id":6,"name":27,"category":28,"favorite":29},"BIM工程师","建筑工程",0]