[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-857208":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},857208,535,1,"单选题","()是一个确保和记录所有的系统和部件都能按照明细和最终用户要求以及业主运营需要执行其相应功能的系统化过程。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目策划",false,{"key":16,"text":17,"correct":18},"B","项目试运行",true,{"key":20,"text":21,"correct":14},"C","项目监督",{"key":23,"text":24,"correct":14},"D","项目总结","项目策划是对实施方案的制定，项目监督是实施过程中对项目的控制，项目总结是在项目完成后对其实施效应的总结归纳。",{"id":6,"name":27,"category":28,"favorite":29},"BIM工程师","建筑工程",0]