[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"lib-53-45":3},{"library":4,"page":9,"limit":10,"total":11,"questions":12,"related":312},{"id":5,"name":6,"category":7,"favorite":8},53,"(初级)建筑与房地产经济","经济金融",0,45,50,2220,[13,38,53,68,82,96,111,126,141,156,168,183,198,212,226,240,254,269,283,297],{"id":14,"libraryId":5,"type":15,"typeLabel":16,"stem":17,"options":18,"answer":36,"analysis":37},52548,2,"多选题","下列影响工程进度的不利因素中，属于建设单位因素的有（ ）。",[19,23,27,30,33],{"key":20,"text":21,"correct":22},"A","不能及时向施工承包单位付款",true,{"key":24,"text":25,"correct":26},"B","组织协调不利，导致停工待料",false,{"key":28,"text":29,"correct":22},"C","由于使用要求改变而进行设计变更",{"key":31,"text":32,"correct":22},"D","提供的场地不能满足工程正常需要",{"key":34,"text":35,"correct":26},"E","邻近工程施工干扰","ACD","",{"id":39,"libraryId":5,"type":15,"typeLabel":16,"stem":40,"options":41,"answer":52,"analysis":37},52549,"建筑工程调整的方法主要有（ ）来缩短工期。",[42,44,46,48,50],{"key":20,"text":43,"correct":22},"压缩某些工作的持续时间",{"key":24,"text":45,"correct":22},"改变某些工作间的逻辑关系",{"key":28,"text":47,"correct":26},"缩短关键线路上的后续工作",{"key":31,"text":49,"correct":26},"调整项目进度计划",{"key":34,"text":51,"correct":26},"变更设计","AB",{"id":54,"libraryId":5,"type":15,"typeLabel":16,"stem":55,"options":56,"answer":67,"analysis":37},52550,"工程实际进度与计划进度的比较方法主要有（ ）。",[57,59,61,63,65],{"key":20,"text":58,"correct":22},"横道图比较法",{"key":24,"text":60,"correct":26},"直方图比较法",{"key":28,"text":62,"correct":22},"S曲线比较法",{"key":31,"text":64,"correct":26},"工程预算比较法",{"key":34,"text":66,"correct":22},"前锋线比较法","ACE",{"id":69,"libraryId":5,"type":15,"typeLabel":16,"stem":70,"options":71,"answer":67,"analysis":37},52551,"某分部工程可划分为甲、乙、丙三个施工过程，其流水节拍分别为3天、6天和12天，若组织成倍节拍流水施工，关于该分部工程流水施工的说法，正确的有（ ）。",[72,74,76,78,80],{"key":20,"text":73,"correct":22},"各个施工过程之间的流水步距均为3天",{"key":24,"text":75,"correct":26},"参加流水作业的专业工作队总数为3队",{"key":28,"text":77,"correct":22},"参加流水作业的专业工作队总数为7队",{"key":31,"text":79,"correct":26},"若取施工段数等于专业工作队总数，则流水施工工期为21天",{"key":34,"text":81,"correct":22},"若取施工段数等于专业工作队总数，则流水施工工期为39天",{"id":83,"libraryId":5,"type":15,"typeLabel":16,"stem":84,"options":85,"answer":67,"analysis":37},52552,"某分部工程可划分为 A、 B、C三个施工过程，分四段组织流水作业，各施工过程在各个流水段上的流水节拍如下表所示（单位：周）。 关于该分部工程流水施工的说法，正确的有（ ）。",[86,88,90,92,94],{"key":20,"text":87,"correct":22},"A．该分部工程宜组织分别流水施工",{"key":24,"text":89,"correct":26},"B． A、 B、C施工过程之间的流水步距为K A，B＝3周、K B，C＝5周",{"key":28,"text":91,"correct":22},"C． A、C施工过程之间的流水步距为KB＝4周、KC＝7周",{"key":31,"text":93,"correct":26},"该分部工程的流水施工工期为22周",{"key":34,"text":95,"correct":22},"该分部工程的流水施工工期为25周",{"id":97,"libraryId":5,"type":15,"typeLabel":16,"stem":98,"options":99,"answer":110,"analysis":37},52553,"在组织流水作业时，划分流水施工段的基本要求有（ ）。",[100,102,104,106,108],{"key":20,"text":101,"correct":22},"有利于保持结构的整体性",{"key":24,"text":103,"correct":22},"为组织连续、均衡施工，各流水段的劳动量应保持大致相等",{"key":28,"text":105,"correct":26},"流水施工段的数量应与参与流水施工的施工过程数相等",{"key":31,"text":107,"correct":26},"参加流水作业的各个施工过程的持续时间必须相同",{"key":34,"text":109,"correct":22},"流水施工段的划分应保证工人施工有足够的工作面","ABE",{"id":112,"libraryId":5,"type":15,"typeLabel":16,"stem":113,"options":114,"answer":125,"analysis":37},52554,"按性质不同，流水施工的主要参数可分为（ ）。",[115,117,119,121,123],{"key":20,"text":116,"correct":26},"技术参数",{"key":24,"text":118,"correct":22},"工艺参数",{"key":28,"text":120,"correct":22},"空间参数",{"key":31,"text":122,"correct":26},"价格参数",{"key":34,"text":124,"correct":22},"时间参数","BCE",{"id":127,"libraryId":5,"type":15,"typeLabel":16,"stem":128,"options":129,"answer":140,"analysis":37},52555,"下列参数中，属于流水施工时间参数的有（ ）。",[130,132,134,136,138],{"key":20,"text":131,"correct":26},"流水段数",{"key":24,"text":133,"correct":26},"施工过程数",{"key":28,"text":135,"correct":22},"流水节拍",{"key":31,"text":137,"correct":22},"流水步距",{"key":34,"text":139,"correct":22},"流水施工工期","CDE",{"id":142,"libraryId":5,"type":15,"typeLabel":16,"stem":143,"options":144,"answer":155,"analysis":37},52556,"下列工程进度的控制措施中，属于组织控制措施的有（ ）。",[145,147,149,151,153],{"key":20,"text":146,"correct":22},"工程进度目标分析、论证、分解",{"key":24,"text":148,"correct":26},"采取加快工程进度的新工艺",{"key":28,"text":150,"correct":26},"协调合同工期与进度计划的关系",{"key":31,"text":152,"correct":22},"建立进度管理工作制度",{"key":34,"text":154,"correct":22},"分析影响进度目标实现的风险因素","ADE",{"id":157,"libraryId":5,"type":15,"typeLabel":16,"stem":158,"options":159,"answer":155,"analysis":37},52557,"下列工程进度控制措施中，属于组织措施的有（ ）。",[160,162,164,165,166],{"key":20,"text":161,"correct":22},"确定进度管理目标体系",{"key":24,"text":163,"correct":26},"选用对实现进度目标有利的技术方案",{"key":28,"text":150,"correct":26},{"key":31,"text":152,"correct":22},{"key":34,"text":167,"correct":22},"编制进度控制工作流程",{"id":169,"libraryId":5,"type":15,"typeLabel":16,"stem":170,"options":171,"answer":182,"analysis":37},52558,"关于施工单位安全生产责任的说法，正确的有（ ）。",[172,174,176,178,180],{"key":20,"text":173,"correct":26},"施工单位的专职安全生产管理人员负责对安全生产进行现场管理",{"key":24,"text":175,"correct":22},"施工单位的项目负责人对建设工程项目的安全施工负责",{"key":28,"text":177,"correct":22},"施工单位应对管理和作业人员每年至少进行一次安全生产教育培训",{"key":31,"text":179,"correct":22},"总承包和分包单位对分包工程的安全生产承担连带责任",{"key":34,"text":181,"correct":22},"施工单位应为施工现场从事危险作业的人员办理意外伤害保险","BCDE",{"id":184,"libraryId":5,"type":15,"typeLabel":16,"stem":185,"options":186,"answer":197,"analysis":37},52559,"下列费用支出项目中，可列入施工企业安全生产费用的有（ ）。",[187,189,191,193,195],{"key":20,"text":188,"correct":22},"现场临时用电安全防护措施支出",{"key":24,"text":190,"correct":22},"现场作业人员安全防护物品支出",{"key":28,"text":192,"correct":22},"配备必要的应急救援器材支出",{"key":31,"text":194,"correct":26},"现场临时办公和生活用房支出",{"key":34,"text":196,"correct":22},"进行应急救援演练支出","ABCE",{"id":199,"libraryId":5,"type":15,"typeLabel":16,"stem":200,"options":201,"answer":140,"analysis":37},52560,"发生下列（ ）事故之一的，不得评为绿色施工合格项目。",[202,204,206,208,210],{"key":20,"text":203,"correct":26},"发生安全生产责任事故",{"key":24,"text":205,"correct":26},"发生直接经济损失100万元的质量事故",{"key":28,"text":207,"correct":22},"发生群体传染病、食物中毒等责任事故",{"key":31,"text":209,"correct":22},"施工中因“环境保护与资源节约”问题被政府管理部门处罚",{"key":34,"text":211,"correct":22},"施工扰民造成社会影响",{"id":213,"libraryId":5,"type":15,"typeLabel":16,"stem":214,"options":215,"answer":197,"analysis":37},52561,"关于施工单位租赁施工机械设备的说法，正确的有（ ）。",[216,218,220,222,224],{"key":20,"text":217,"correct":22},"施工机械设备应当具有生产（制造）许可证",{"key":24,"text":219,"correct":22},"施工机械设备应当具有产品合格证",{"key":28,"text":221,"correct":22},"施工机械设备进入施工现场前应进行查验",{"key":31,"text":223,"correct":26},"施工机械设备进入施工现场后应进行查验",{"key":34,"text":225,"correct":22},"施工现场应建立施工机械设备相应的资料档案",{"id":227,"libraryId":5,"type":15,"typeLabel":16,"stem":228,"options":229,"answer":197,"analysis":37},52562,"施工安全技术交底应包括的主要内容有（ ）。",[230,232,234,236,238],{"key":20,"text":231,"correct":22},"工程项目施工作业特点和危险点",{"key":24,"text":233,"correct":22},"针对危险点的具体预防措施",{"key":28,"text":235,"correct":22},"相应安全操作规程和标准",{"key":31,"text":237,"correct":26},"安全生产管理制度",{"key":34,"text":239,"correct":22},"发生事故后应及时采取的避难和急救措施",{"id":241,"libraryId":5,"type":15,"typeLabel":16,"stem":242,"options":243,"answer":110,"analysis":37},52563,"绿色施工的评价指标由（ ）组成。",[244,246,248,250,252],{"key":20,"text":245,"correct":22},"控制项",{"key":24,"text":247,"correct":22},"一般项",{"key":28,"text":249,"correct":26},"优良项",{"key":31,"text":251,"correct":26},"合格项",{"key":34,"text":253,"correct":22},"优选项",{"id":255,"libraryId":5,"type":15,"typeLabel":16,"stem":256,"options":257,"answer":268,"analysis":37},52564,"在工程项目管理信息系统功能中，属于进度控制子系统功能的有（ ）。",[258,260,262,264,266],{"key":20,"text":259,"correct":22},"编制多平面群体网络计划",{"key":24,"text":261,"correct":22},"工程进度各类数据的查询",{"key":28,"text":263,"correct":22},"工程实际进度的统计分析",{"key":31,"text":265,"correct":22},"提供针对不同管理平面的工程进度报表",{"key":34,"text":267,"correct":26},"项目概算与预算的对比分析","ABCD",{"id":270,"libraryId":5,"type":15,"typeLabel":16,"stem":271,"options":272,"answer":182,"analysis":37},52565,"工程项目信息包括（ ）。",[273,275,277,279,281],{"key":20,"text":274,"correct":26},"项目的资源类信息",{"key":24,"text":276,"correct":22},"项目的管理类信息",{"key":28,"text":278,"correct":22},"项目的经济类信息",{"key":31,"text":280,"correct":22},"项目的技术类信息",{"key":34,"text":282,"correct":22},"项目的组织类信息",{"id":284,"libraryId":5,"type":15,"typeLabel":16,"stem":285,"options":286,"answer":36,"analysis":37},52566,"项目信息门户的核心功能包括（ ）。",[287,289,291,293,295],{"key":20,"text":288,"correct":22},"项目各参与方的信息交流",{"key":24,"text":290,"correct":26},"合同管理",{"key":28,"text":292,"correct":22},"项目各参与方的协同工作",{"key":31,"text":294,"correct":22},"项目文档管理",{"key":34,"text":296,"correct":26},"风险管理",{"id":298,"libraryId":5,"type":15,"typeLabel":16,"stem":299,"options":300,"answer":311,"analysis":37},52567,"在建设工程项目管理信息化中，项目信息门户的意义主要表现在（ ）方面。",[301,303,305,307,309],{"key":20,"text":302,"correct":22},"有利于降低工程项目实施成本",{"key":24,"text":304,"correct":26},"有利于提高项目效率",{"key":28,"text":306,"correct":22},"有利于缩短项目建设时间",{"key":31,"text":308,"correct":22},"有利于提高工程建设质量",{"key":34,"text":310,"correct":22},"有利于降低工程实施风险","ACDE",[313,317,320,323,326,328],{"id":314,"name":315,"category":7,"favorite":316},109,"发布证券研究报告业务",1,{"id":318,"name":319,"category":7,"favorite":8},30,"经济师",{"id":321,"name":322,"category":7,"favorite":8},31,"(初级)银行从业资格",{"id":324,"name":325,"category":7,"favorite":8},49,"初级经济师",{"id":10,"name":327,"category":7,"favorite":8},"(初级)保险专业",{"id":329,"name":330,"category":7,"favorite":8},51,"(初级)财政税收"]