[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52564":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52564,53,2,"多选题","在工程项目管理信息系统功能中，属于进度控制子系统功能的有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","编制多平面群体网络计划",true,{"key":16,"text":17,"correct":14},"B","工程进度各类数据的查询",{"key":19,"text":20,"correct":14},"C","工程实际进度的统计分析",{"key":22,"text":23,"correct":14},"D","提供针对不同管理平面的工程进度报表",{"key":25,"text":26,"correct":27},"E","项目概算与预算的对比分析",false,"ABCD","进度控制子系统的基本功能是编制双代号网络计划、单代号搭接网络计划和多平面群体网络计划，进行工程实际进度的统计分析、实际进度与计划进度的动态比较、工程进度变化趋势预测、计划进度的定期调整、工程进度各类数据的查询，提供针对不同管理平面的工程进度报表，绘制网络图和横道图等。E项属于投资（成本）控制子系统的功能。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]