[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52557":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52557,53,2,"多选题","下列工程进度控制措施中，属于组织措施的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","确定进度管理目标体系",true,{"key":16,"text":17,"correct":18},"B","选用对实现进度目标有利的技术方案",false,{"key":20,"text":21,"correct":18},"C","协调合同工期与进度计划的关系",{"key":23,"text":24,"correct":14},"D","建立进度管理工作制度",{"key":26,"text":27,"correct":14},"E","编制进度控制工作流程","ADE","进度控制的组织措施主要包括：建立相应的进度管理组织机构，并由专门的工作部门和符合进度控制岗位资格的专人负责进度控制工作；分析、论证和分解工程进度目标，形成进度管理目标体系；编制进度计划和进度控制工作流程、建立进度管理工作制度；分析影响进度目标实现的干扰和风险因素等。B项是技术措施；C项是合同措施。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]