[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52555":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52555,53,2,"多选题","下列参数中，属于流水施工时间参数的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","流水段数",false,{"key":16,"text":17,"correct":14},"B","施工过程数",{"key":19,"text":20,"correct":21},"C","流水节拍",true,{"key":23,"text":24,"correct":21},"D","流水步距",{"key":26,"text":27,"correct":21},"E","流水施工工期","CDE","流水施工的主要参数，按其性质的不同，一般可以分为：工艺参数、空间参数和时间参数三种类型。在组织流水施工时，用以表达流水施工在时间排列上所处状态的参数，称为时间参数。时间参数主要包括：流水节拍、流水步距、流水施工工期等。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]