[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52553":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52553,53,2,"多选题","在组织流水作业时，划分流水施工段的基本要求有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","有利于保持结构的整体性",true,{"key":16,"text":17,"correct":14},"B","为组织连续、均衡施工，各流水段的劳动量应保持大致相等",{"key":19,"text":20,"correct":21},"C","流水施工段的数量应与参与流水施工的施工过程数相等",false,{"key":23,"text":24,"correct":21},"D","参加流水作业的各个施工过程的持续时间必须相同",{"key":26,"text":27,"correct":14},"E","流水施工段的划分应保证工人施工有足够的工作面","ABE","划分施工段的基本要求包括：①有利于保持结构的整体性；②各施工段的劳动量相等或大致相等；③要有足够的工作面；④施工段数目应与主导施工过程相协调；⑤组织多层建筑物流水施工时，施工段数应大于或等于施工过程数。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]