[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52551":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52551,53,2,"多选题","某分部工程可划分为甲、乙、丙三个施工过程，其流水节拍分别为3天、6天和12天，若组织成倍节拍流水施工，关于该分部工程流水施工的说法，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","各个施工过程之间的流水步距均为3天",true,{"key":16,"text":17,"correct":18},"B","参加流水作业的专业工作队总数为3队",false,{"key":20,"text":21,"correct":14},"C","参加流水作业的专业工作队总数为7队",{"key":23,"text":24,"correct":18},"D","若取施工段数等于专业工作队总数，则流水施工工期为21天",{"key":26,"text":27,"correct":14},"E","若取施工段数等于专业工作队总数，则流水施工工期为39天","ACE","A项，流水步距K可取各流水节拍的最大公约数，甲乙丙流水节拍分别为3天，6天，12天，则K＝3（天）。BC两项，各施工过程的专业工作队数bi＝ti\u002FK（ti为第i个施工过程的流水节拍），所以b1＝t1\u002FK＝3÷3＝1（队），b2＝t2\u002FK＝6÷3＝2（队），b3＝t3\u002FK＝12÷3＝4（队）。故参加流水作业的专业工作队总数为N＝b1＋b2＋b3＝1＋2＋4＝7（队）。DE两项，若取施工段数等于专业工作队总数，则m＝N＝7（段）。故流水施工工期为：T＝（m＋N－1）K＝（7＋7－1）×3＝39（天）。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]