[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52550":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52550,53,2,"多选题","工程实际进度与计划进度的比较方法主要有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","横道图比较法",true,{"key":16,"text":17,"correct":18},"B","直方图比较法",false,{"key":20,"text":21,"correct":14},"C","S曲线比较法",{"key":23,"text":24,"correct":18},"D","工程预算比较法",{"key":26,"text":27,"correct":14},"E","前锋线比较法","ACE","比较工程实际进度与计划进度的常用方法有：①横道图比较法，是最常用的比较方法，它是指用横道图编制工程进度计划，并将工程实施过程中检查实际进度收集的数据、信息，经过加工整理后直接用横道线平行绘制于原进度计划横道线下面，用两种图例进行对比，可以直观、清楚地反映工程实际进度与计划进度的对比情况；②S曲线比较法，指以横坐标表示时间，纵坐标表示累计完成工程量，进行实际进度与计划进度比较的一种方法；③前锋线比较法，指在时标网络计划中，根据某检查时刻各项工作的实际进展状况绘制一条实际进度前锋线，将工程计划进度与实际进度进行比较的方法。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]