[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52549":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52549,53,2,"多选题","建筑工程调整的方法主要有（ ）来缩短工期。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","压缩某些工作的持续时间",true,{"key":16,"text":17,"correct":14},"B","改变某些工作间的逻辑关系",{"key":19,"text":20,"correct":21},"C","缩短关键线路上的后续工作",false,{"key":23,"text":24,"correct":21},"D","调整项目进度计划",{"key":26,"text":27,"correct":21},"E","变更设计","AB","当实际进度偏差影响到后续工作、总工期需要调整进度计划时，其调整方法主要有两种：①通过压缩某些工作的持续时间来缩短工期；②通过改变某些工作间的逻辑关系来缩短工期。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]