[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52548":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52548,53,2,"多选题","下列影响工程进度的不利因素中，属于建设单位因素的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","不能及时向施工承包单位付款",true,{"key":16,"text":17,"correct":18},"B","组织协调不利，导致停工待料",false,{"key":20,"text":21,"correct":14},"C","由于使用要求改变而进行设计变更",{"key":23,"text":24,"correct":14},"D","提供的场地不能满足工程正常需要",{"key":26,"text":27,"correct":18},"E","邻近工程施工干扰","ACD","在工程建设过程中，影响工程进度的建设单位因素包括：如建设单位使用要求改变而进行设计变更，应提供的施工场地条件不能及时提供或所提供的场地不能满足工程正常需要，不能及时向施工承包单位或材料供应商付款等。B项属于组织管理因素；E项属于社会环境因素。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]