[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52547":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52547,53,2,"多选题","下列工作内容中，属于工程进度计划执行情况跟踪检查工作内容的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","确定进度目标并落实责任",false,{"key":16,"text":17,"correct":14},"B","编制进度计划及资源计划",{"key":19,"text":20,"correct":21},"C","建立进度数据采集系统",true,{"key":23,"text":24,"correct":21},"D","收集实际进度数据及数据处理",{"key":26,"text":27,"correct":21},"E","实际进度与计划进度的比较","CDE","在工程进度计划实施过程中，应经常、定期地对进度计划执行情况进行跟踪检查，以便发现问题，及时采取措施加以解决。进度计划的检查程序主要包括：①建立进度数据采集系统；②收集实际进度数据；③数据处理；④实际进度与计划进度的比较。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]