[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52546":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52546,53,2,"多选题","某分部工程可划分为 A、 B、C三个施工过程，分三段组织流水作业， A、 B、C三个施工过程在各个流水段上的流水节拍依次为：4、5、4；3、3、2；4、3、4（单位：天）。 A、 B、C三个施工过程之间的流水步距和其流水施工工期分别为（ ）天。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","3",true,{"key":16,"text":17,"correct":18},"B","5",false,{"key":20,"text":21,"correct":14},"C","7",{"key":23,"text":24,"correct":14},"D","21",{"key":26,"text":27,"correct":18},"E","31","ACD","根据已知条件，本工程宜组织分别流水施工。计算过程如下： ①求各施工过程流水节拍的累加数列。A：4 9 13，B：3 6 8，C：4 7 11。 ②将相邻两个施工过程的累加数列错位相减。A与B： ③确定流水步距。流水步距等于各累加数列错位相减所得差值中数值最大者，即：K1，2＝max（4，6，7，－8）＝7（天），K2，3＝max（3，2，1，－11）＝3（天）。 ④计算流水施工工期：T＝∑Ki,j＋1＋∑t3j＝（3＋7）＋（4＋3＋4）＝21（天）。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]