[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52543":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52543,53,2,"多选题","下列工程进度控制的措施中，属于经济措施的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","编制与进度计划相协调的资源需求计划",true,{"key":16,"text":17,"correct":18},"B","选用有利于进度目标实现的设计和施工技术方案",false,{"key":20,"text":21,"correct":18},"C","分析影响进度目标实现的干扰和风险因素",{"key":23,"text":24,"correct":14},"D","落实实现进度目标的建设资金",{"key":26,"text":27,"correct":14},"E","建立工期超前或延误的奖惩机制","ADE","通常采取的进度控制措施有组织措施、技术措施、经济措施、合同措施和信息管理措施。其中，进度控制的经济措施主要包括：①编制与进度计划相协调的资源需求计划（包括资金需求计划和人、材、机等资源需求计划），以反映工程实施各时段所需要的资源，保证进度计划实现的可能性；②落实实现进度目标的建设资金，保证工程项目用款能及时拨付；③对应急赶工应给予相应的赶工费用补偿、对工期超前或延误建立相应的奖惩机制。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]