[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52542":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52542,53,2,"多选题","工程项目建设总进度计划是对工程项目从开始建设（设计、施工准备）至竣工投产（动用）全过程的统一部署，其主要内容有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","投资计划年度分配表",true,{"key":16,"text":17,"correct":14},"B","工程项目总进度计划表",{"key":19,"text":20,"correct":14},"C","工程项目一览表",{"key":22,"text":23,"correct":24},"D","年度建设资金平衡表",false,{"key":26,"text":27,"correct":14},"E","工程项目进度平衡表","ABCE","工程建设总进度计划是指工程项目决策立项后，对工程项目从开始建设（设计、施工准备）至竣工投产（动用）全过程的统一部署。其主要目的是安排各单位工程建设进度，合理分配年度投资，组织各方面的协作，保证工程建设各项任务的完成。工程建设总进度计划除编制说明外，主要包括：①工程项目一览表；②工程项目总进度计划表；③投资计划年度分配表；④工程项目进度平衡表。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]