[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52538":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52538,53,2,"多选题","工人在工作班内消耗的工作时间中，属于损失时间的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","休息时间",false,{"key":16,"text":17,"correct":18},"B","多余工作时间",true,{"key":20,"text":21,"correct":18},"C","偶然工作时间",{"key":23,"text":24,"correct":18},"D","停工时间",{"key":26,"text":27,"correct":18},"E","违背劳动纪律损失的时间","BCDE","损失时间是指与产品生产无关、而与施工组织和技术上的缺陷有关，与工人在施工过程中的个人过失或某些偶然因素有关的时间消耗，包括：①多余和偶然工作时间；②停工时间；③违背劳动纪律损失的时间。A项属于必需消耗的工作时间。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]