[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52535":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52535,53,2,"多选题","工程建设定额中，属于按生产要素消耗内容分类的定额有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工定额",false,{"key":16,"text":17,"correct":18},"B","劳动定额",true,{"key":20,"text":21,"correct":14},"C","预算定额",{"key":23,"text":24,"correct":18},"D","材料消耗定额",{"key":26,"text":27,"correct":18},"E","施工机具台班消耗定额","BDE","按照定额所反映的生产要素消耗内容分类，工程定额可分为：①劳动定额，是指在正常施工技术和组织条件下，完成单位合格产品所必需的人工消耗量标准。②材料消耗定额，是指在合理和节约使用的条件下，生产单位合格产品所必需消耗的一定规格的材料、成品、半成品和水、电等资源的数量标准。③施工机具台班消耗定额，是指施工机械和仪器仪表在正常施工条件下完成单位合格产品所必需的工作时间。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]