[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52532":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52532,53,2,"多选题","为有效控制工程造价，应将工程造价管理的重点放在（ ）阶段。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","施工招标",false,{"key":16,"text":17,"correct":14},"B","施工",{"key":19,"text":20,"correct":21},"C","策划决策",true,{"key":23,"text":24,"correct":21},"D","工程设计",{"key":26,"text":27,"correct":14},"E","竣工验收","CD","长期以来，我国往往将控制工程造价的主要精力放在施工阶段—审核施工图预算、结算建筑安装工程价款，对工程项目策划决策和工程设计阶段的造价控制重视不够。为有效地控制工程造价，应将工程造价管理的重点转到工程项目策划决策和工程设计阶段。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]