[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52530":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52530,53,2,"多选题","下列工程项目施工过程发生的费用中，属于直接成本的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","建筑安装工人工资",true,{"key":16,"text":17,"correct":18},"B","项目管理人员工资",false,{"key":20,"text":21,"correct":18},"C","项目部劳动保护费",{"key":23,"text":24,"correct":14},"D","施工机具安装和拆卸使用费",{"key":26,"text":27,"correct":18},"E","差旅费","AD","直接成本是指施工过程中直接耗费的构成工程实体或有助于工程形成的各项支出，包括人工费、材料费、施工机具使用费和其他直接费（即措施费）。BCE三项属于间接成本。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]