[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52523":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52523,53,2,"多选题","下列工人工作时间中，属于损失时间的有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","停工时间",true,{"key":16,"text":17,"correct":14},"B","多余和偶然工作时间",{"key":19,"text":20,"correct":14},"C","违背劳动纪律损失时间",{"key":22,"text":23,"correct":24},"D","基本工作时间",false,{"key":26,"text":27,"correct":24},"E","辅助工作时间","ABC","损失时间是指与产品生产无关、而与施工组织和技术上的缺陷，以及工人在施工过程中的个人过失或与某些偶然因素有关的时间消耗，包括：①多余和偶然工作时间；②停工时间；③违背劳动纪律损失的时间。CD两项属于有效工作时间。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]