[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52514":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52514,53,2,"多选题","施工准备阶段质量管理的主要内容有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","工程定位和标高基准控制",true,{"key":16,"text":17,"correct":14},"B","施工平面布置控制",{"key":19,"text":20,"correct":14},"C","材料质量控制",{"key":22,"text":23,"correct":14},"D","施工机械设备质量控制",{"key":25,"text":26,"correct":27},"E","关键部位和关键工序质量控制",false,"ABCD","施工准备阶段质量管理的内容有：①工程定位和标高基准控制；②施工平面布置控制；③材料质量控制；④施工机械设备质量控制。施工过程质量管理的内容有：①技术交底；②测量控制；③计量控制；④工序施工质量控制；⑤关键部位和关键工序质量控制；⑥成品保护。E项属于施工过程质量管理的内容。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]